![]() |
| A construction company was paid a total of $500,000 for a .. |
| Re: A construction company was paid a total of $500,000 for |
|
Ron Purewal
MGMAT STAFF
|
(1) alone: since total cost = L + M, this means that L + M = 3M, or L = 2M. so, rephrased, statement 1 says that labor cost twice as much as materials. still, this is insufficient, as picking values will show: if M = $1 and L = $2, the answer is yes, but if M = $150,000 and L = $300,000, the answer is no. (2) alone: great, but no information at all about materials. so, if L = M = $1, then yes; if L = $1 and M = $499,997 (so that profit = $2), then no. insufficient together: we have P > L which, using the rephrasing found above, rephrases to P > 2M also, P = 500,000 - 3M (because total cost = 3M) so 500,000 - 3M > 2M 500,000 > 5M 100,000 > M since M is less than 100,000, it follows that profit, which is 500,000 - 3M, must be more than 500,000 - 3(100,000) = 200,000. answer = yes sufficient this is a hard problem! |
||||||||||||||
|
|
|||||||||||||||
| Thanks |
|
Steve G
Guest
|
Thanks on this one as well Ron! Makes sense.
|
||||||||||||
|
|
|||||||||||||
|
guest
Guest
|
Could you do the problem this way as well
Stmt 1) Labor cost is twice the cost of material -> 2M+M = 500000 => M=500000/3 => L = 2* 500003/3 = 333333.333. Nothing is known about Profit. INSUFF Stmt 2) Profit is larger than Labor cost -> But nothing is know about the labor cost. INSUFF Combine (1) and (2) -> Profit is greater than L => P > 333333.333. Hence P > 150000. SUFF (C) |
||||||||||||
|
|
|||||||||||||
|
Ron Purewal
MGMAT STAFF
|
nope, can't do it that way. the company's revenue for the construction project, not its total cost, was $500k. the m + 2m = 3m is the total cost of materials and labor; if you set 3m equal to $500k, you're implying that the total costs are $500k. in that case, since you already know that the revenue is $500k, you'd have zero profit. remember: profit = revenue - cost (this is the only thing you'll ever have to know on the gmat that pertains even remotely to business) the whole point of statement (1) is that you have no actual dollar value for the total cost. if you had a concrete dollar value - any dollar value, regardless of the actual amount - you'd be able to calculate the profit. |
||||||||||||||
|
|
|||||||||||||||
| A construction company was paid a total of $500,000 for a .. |
|
||
|
Powered by phpBB © phpBB Group
Content © Manhattan GMAT Forums
*GMAT and GMAT CAT are registered trademarks of the Graduate Management Admission Council,
which neither sponsors nor endorses this test preparation service.
Content © Manhattan GMAT Forums
*GMAT and GMAT CAT are registered trademarks of the Graduate Management Admission Council,
which neither sponsors nor endorses this test preparation service.


