Could please somebody explain solution of the problem?

A company has two types of machines, type R and type S. Operating as a constant rate, a machine R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company used the same number of machines to do the job in 2 hours, how many machines of type R were used?

A. 3
B. 4
C. 6
D. 9
E. 12

The correct answer is C. 6.

Thanks!


Top 
 Post subject: Re: A company has two types of machines, type R and type S
 Post Posted: Sun Nov 11, 2007 8:44 pm 
Guest wrote:
Could please somebody explain solution of the problem?

A company has two types of machines, type R and type S. Operating as a constant rate, a machine R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company used the same number of machines to do the job in 2 hours, how many machines of type R were used?

A. 3
B. 4
C. 6
D. 9
E. 12

The correct answer is C. 6.

Thanks!


Machine R can do 1 job / 36hrs. S does 1 job / 18 hrs. We want the total to be 1 job / 2hrs

So this is the equation where x represents the number of machines you need:

rate of R + rate of S = rate of total
x/36 + x/18 = 1/2
(multiply all by 36)
x + 2x = 18
3x = 18
x = 6 machines


Top 
 Post subject:
 Post Posted: Fri Nov 16, 2007 6:47 am 
Offline
ManhattanGMAT Staff


Posts: 7146
That's it.

There are some ways to streamline this problem - such as using a 'rate chart' with (work rate) x (time) = (total work done) - but the essence of the problem will still be exactly what's here.


Top 
 Post subject:
 Post Posted: Wed Nov 21, 2007 7:26 pm 
I have it is saying how many type of R machine used. I presume 6 means ( same no. of S + same no. of R)


so total number of R machine should be 3. Please correct if I am wrong


Top 
 Post subject:
 Post Posted: Wed Nov 21, 2007 8:12 pm 
Let me correct I post wrong 3 Answer is 6

It is like this

In 12 hours R + S can finish a job

so in 1 hours the set finish 1/12 of the work

in 2hours the set (R + S) finish 1/6 of the work

so inorder to finish full work we need 6 sets of (R+S).
Hence R machine needed R=6


Top 
 Post subject:
 Post Posted: Thu Nov 22, 2007 3:47 am 
Offline
ManhattanGMAT Staff


Posts: 7146
Yep - if you look at the setup of the algebra done earlier in the post, you'll notice that the equation includes 'x' of machine R *AND* 'x' of machine S.


Top 
 Post subject:
 Post Posted: Tue Nov 27, 2007 12:39 pm 
When I set this problem up I had it like this: x/36 + y/18 = 1/2. Where x and y where the number of each type of machine.

If the company used the same number of machines to do the job in 2 hours, how many machines of type R were used?

Where it says same number of machines, can that be interpreted as the same number of machine r as the number of machine s?

Kind of crucial wording that totally screwed me up.[/b][/i]


Top 
 Post subject:
 Post Posted: Fri Nov 30, 2007 5:16 am 
Offline
ManhattanGMAT Staff


Posts: 7146
Anonymous wrote:
Where it says same number of machines, can that be interpreted as the same number of machine r as the number of machine s?


I'm assuming that was a typo - a 'streamlined' version of the original question that obfuscates its original meaning. Interestingly, I didn't even notice that when I responded to this thread earlier.

Moreover, that's what the problem has to mean; otherwise, there are many combinations of machines that will solve the problem, as machine S is exactly twice as fast as machine R: we could just take away one machine S and replace it with two R's (or vice versa), and the new combination would also work. Since this isn't data sufficiency (i.e., we need a UNIQUE solution), that won't do.


Top 
 Post subject:
 Post Posted: Sun Jun 15, 2008 6:44 pm 
------------1 machines-----1 machines
Rate-----------Rr---------------Sr----------

Time --------36----------------18---------(hrs)

Work--------1 job-----------1 job

W=rt

1*36*Rr=1*18*Sr

Sr=2*Rr

------------x machines-----x machines -----(Same machines)
Rate-----------Rr---------------Sr----------

Time --------2----------------2---------(hrs)

Work--------1 job-----Total work done by both machines

Work=2*Rr*x+2*Sr*x
=2x(Rr+Sr)
=2x(3Rr) ---Since Sr=2Rr
=6xRr

6xRr=36Rr ---job done by Rr from step 1

 x=6


Top 
 Post subject: R&S
 Post Posted: Wed Jun 18, 2008 4:11 am 
assume the task is to lay bricks so R - 1 brick per hour =36 hours : s 2 bricks per hour = 18 hours the ratio is 2:1

hence inorder to do the job in 2 hours need to lay 18 bvricks per hour in the ratio 1:2 hence the answer is 6


Top 
 Post subject:
 Post Posted: Wed Jun 18, 2008 5:19 am 
Offline
ManhattanGMAT Staff


Posts: 7146
nice wealth of solutions to this problem.
sweetness


Top 
 Post subject:
 Post Posted: Mon Aug 04, 2008 1:21 pm 
m seein complex solutions here :)
in one hour machine a does 1/36 B does 1/ 18
one hour combined 1/36 + 1/18 = 1/12 ----> 1 hour
2 hours amount of wok done = 2/12 == 1/ 6

since num of machines is the same it shud be 6 .....


Top 
 Post subject:
 Post Posted: Wed Aug 13, 2008 3:37 am 
Offline
ManhattanGMAT Staff


Posts: 7146
Anonymous wrote:
m seein complex solutions here :)
in one hour machine a does 1/36 B does 1/ 18
one hour combined 1/36 + 1/18 = 1/12 ----> 1 hour
2 hours amount of wok done = 2/12 == 1/ 6

since num of machines is the same it shud be 6 .....


this is a nice compact solution.

next time, please write out words in full, so that your posts are easier to read. thank you.


Top 
 Post subject: Re: A company has two types of machines, type R and type S
 Post Posted: Wed Feb 09, 2011 1:48 pm 
Offline
Course Students


Posts: 34
Instr.
When I do (1/36+1/18)*2=1/6
Combined rates of each mach. respect. mult. 2 hours. How can I derive from 1/6 , 6 machines?
Thanks


Top 
 Post subject: Re: A company has two types of machines, type R and type S
 Post Posted: Fri Feb 11, 2011 6:12 am 
Offline
ManhattanGMAT Staff


Posts: 7146
alexei600 wrote:
Combined rates of each mach. respect. mult. 2 hours.


i don't know what this is supposed to say; please re-type your post in complete sentences, with words that are not abbreviated. thanks much.


Top 
Display posts from previous:  Sort by  
 
 Page 1 of 2 [ 19 posts ] Go to page 1, 2  Next





Who is online

Users browsing this forum: No registered users and 0 guests

 
 

 
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to: